top of page
clear-bg.png

HEALTH & SAFETY

PSDP

PSDP

As a Project Supervisor Design Process (PSDP), SHD will undertake to:

Identify hazards arising from the design or from the technical, organisational, planning or time related aspects of the project;

•Where possible, eliminate the hazards or reduce the risk;

•Communicate necessary control measures, design assumptions, or remaining risks to the PSCS so they can be dealt with in the Safety and Health Plan;

•Ensure that the work of designers is co-ordinated to ensure safety;

•Organise co-operation between designers;

•Prepare a written safety and health plan for any project where construction will take more than 500 person days or 30 working days or there is a Particular Risk and deliver it to the client prior to tender;

•Prepare a safety file for the completed structure and give it to the client;

•Notify the Authority and client of non-compliance with any written directions issued;

•The PSDP may issue directions to designers or contractors or others.

bottom of page