As a Project Supervisor Design Process (PSDP), SHD will undertake to:
•Identify hazards arising from the design or from the technical, organisational, planning or time related aspects of the project;
•Where possible, eliminate the hazards or reduce the risk;
•Communicate necessary control measures, design assumptions, or remaining risks to the PSCS so they can be dealt with in the Safety and Health Plan;
•Ensure that the work of designers is co-ordinated to ensure safety;
•Organise co-operation between designers;
•Prepare a written safety and health plan for any project where construction will take more than 500 person days or 30 working days or there is a Particular Risk and deliver it to the client prior to tender;
•Prepare a safety file for the completed structure and give it to the client;
•Notify the Authority and client of non-compliance with any written directions issued;
•The PSDP may issue directions to designers or contractors or others.